Satisfied ITS Customers - Hitzkirchertal
Available 24/7 Emergency


0800 678 800
Zurück zur Übersicht

Hitzkirchertal

The Hitzkirchertal extends in the Lucerne Seetal between the Baldeggersee and Hallwilersee and includes the municipalities of Hitzkirch and the districts of Altwis, Gelfingen, Hämikon, Mosen, Müswangen, Retschwil, Richensee and Sulz.

Problemstellung

In the case of a sewer section with significant damage (cracks, holes, sockets), a comprehensive renovation was necessary. Due to the dimensions (DN 600–900 mm) and the location – partly on private property and difficult-to-access fields – the implementation represented a logistical and technical challenge. In addition, the water flow had to be coordinated with the responsible sewage treatment plant during the work.

Lösung

iTS Kanal Services AG used state-of-the-art robotic rehabilitation methods (milling, crack and hole treatment, socket rehabilitation). This was supplemented by the use of Quick-Lock systems and Alphaliner liner technology for large-dimensioned supports. Close consulting and planning support enabled the originally planned renovation measures to be adapted and optimized. Some of the work was carried out under the supervision of a traffic service to ensure safety and coordination in public spaces.

Stephan Zihlmann

Project Manager
"The company ITS also takes care of problems that arise after high-quality work has been carried out. You get support and solutions are sought."

Zufriedenheit

The combination of technical competence and practical advice led to efficient, on-schedule implementation. Despite difficult access to the manholes and the need for coordination with third parties (traffic service, sewage treatment plant, farmers), the renovation was successfully completed. Clients and stakeholders benefited from clear communication and flexible adaptation of measures.

Nutzern

  • Sustainable renovation through the use of state-of-the-art processes (Quick-Lock, Alphaliner)
  • Optimized measures thanks to expert advice
  • Ensuring water flow through cooperation with the sewage treatment plant
  • Successful implementation despite difficult access to the manholes
  • High operational reliability and extension of the service life of the sewage system

Weitere Erfolgsgeschichten